Description : | Demolition of Old Dilapidated UndergroundSump, Pump House, Panel room & other structure, replace existing Damagepipe line And Construction of New 36.70 Lakh Liter U/G Sump, Pump House,Chlorination Room, Chlorinator, And other Allied works at Gulabnagar, ForJamnagar Water Supply Scheme, Jamnagar. District: Jamnagar, Gujarat. |
Budget Provision | 15thFinance Commission Grant |
Estimated Expense(Rs. in Lacs) | 1,86,80,017=00 |
Contractor Name | Seagull Infracone PvtLtd, Rajkot |
Project Start Date | 17-09-2021 |
Percentage of Work Completed | 80% |
Estimated Date of Work Completion | 16-03-2023 |
Remark | Work in progress |
|
Description : | PROVIDING,SUPPLYING, LOWERING, LAYING, JOINTING, FIXING AND TESTING DI–K7 PIPELINEFOR WATER DISTRIBUTION NETWORK INCLUDING CONSTRUCTION OF VALVE CHAMBER ,FITTING OF VALVES, CONNECTIONWITH EXISTING PIPELINE AND ALLIED WORK IN DIFFERENT CITY AREAS OF ZONAL ESR OFJAMNAGAR MUNICIPAL CORPORATION |
Budget Provision | 15thFinance Commission Grant |
Estimated Expense(Rs. in Lacs) | 9,82,92,204=00 |
Contractor Name | Tapan InfrastructureCo, Rajkot |
Project Start Date | 28-06-2022 |
Percentage of Work Completed | 35% |
Estimated Date of Work Completion | 27-06-2023 |
Remark | Work in progress |
|
Description : | Providing, supplying, lowering, laying, jointing,fixing and testing DI-K7 pipeline for distribution network including construction of valve chamber ,fitting ofvalves, making job connection of existing pipe & new pipe and road resurfacing work with 3 monthstrial run etc in Mahaprabhuji area for Jamnagar water supply scheme.District: Jamnagar, Gujarat |
Budget Provision | SJMMSVY- NAL SE JALand 15th FC Grant |
Estimated Expense(Rs. in Lacs) | 21,02,48,552=00 |
Contractor Name | KSD Construction, Rajkot |
Project Start Date | 21-07-2022 |
Percentage of Work Completed | 35% |
Estimated Date of Work Completion | 20-01-2024 |
Remark | Work in progress |
|
Description : | Providing, supplying, lowering, laying, jointing, fixing and testing DI-K7 pipeline for distribution network including construction of valve chamber, fitting of valves, and road resurfacing work with 3 months trial run etc. in Gokulnagar & Samarpan area for Jamnagar water supply scheme. District: Jamnagar, Gujarat |
Budget Provision | SJMMSVY- NAL SE JALGrant |
Estimated Expense(Rs. in Lacs) | 29,76,25,517=00 |
Contractor Name | KSD Construction, Rajkot |
Project Start Date | 21-07-2022 |
Percentage of Work Completed | 30% |
Estimated Date of Work Completion | 20-01-2024 |
Remark | Work in progress |
|